|
Building Updates on AUB Campus
 |
| School of Nursing |
The new Suliman S. Olayan School of Business building is expected to
be complete by the end of January 2009. The building structure on AUB's
lower campus and external works are complete, while the addition of all
masonry work and plastering, steel structure erection, and steel doors
and frames have been finalized. Stone cladding work for all the facades
are 60 percent complete, and mechanical and electrical work is in progress.
Currently, the ongoing work includes the installation of panel boards
and main equipment, such as UPS and transformers.
As for the Issam Fares Institute for Public Policy and International
Affairs, which will become a venue for international researchers and
scholars, the new structure will replace the Gulbekian Infirmary building,
formerly occupied by the University Health Services. While the Gulbekian
is currently being pulled down, the process of comprehensive design for
the site is in progress and is expected to be completed by June 2009.
Construction will be executed by April 2011.
The School of Nursing plans to move to its new building upon its
completion in November 2008. The final stages of completion of construction
work are underway, after which the contractor will complete the internal
testing and commissioning stage.
|